Amtrak’s Harrisburg Line Track Renewal Project Moves to Second Phase on Monday, April 29

Download image [1]

New minor schedule adjustments will be implemented for some Keystone Service trains

HARRISBURG, Pa. – Amtrak’s Harrisburg Line Track Renewal Project in Pennsylvania [2] that began in March is well underway and moving to Phase 2 on Monday, April 29.

As a result, additional minor schedule changes will be implemented for some Keystone Service [3] trains, ranging from 2-17 minutes on weekdays and 5-35 minutes on weekends. Pennsylvanian [4] train schedules will not be affected.

This $122 million project between Lancaster and Harrisburg would normally take approximately two years, but Amtrak is taking an innovative approach with single and full track outages to improve work efficiencies and reduce the duration of customer impacts. Amtrak will continue to keep customers updated as work moves through various phases. The project is scheduled to conclude in November.

Customers should check Amtrak.com [5] or the Amtrak mobile app [6] for the latest schedules.

Overview of Upcoming Schedule Changes

Monday-Thursday (beginning April 29)

Friday (beginning May 3)

Saturday & Sunday (beginning May 4-5)